Attend a site meeting at PK AGRO Site on 26th May 2010. This site meeting as usual highlighted the weekly progress and works done by the contractors. Issues highlighted such as the cables used by electrical contractor are not according to the owner requirement and asked to change it. Some of the wall plugs used are not stainless steel and rectification needed.
Then around 3pm, I went for a client meeting at SEHWA ELECTRONIC, Senawang. This meeting is for the extension building of SEHWA and layout of new factory. The matters discussed such as changes/additional areas, power supply and warehouse location.
I then continued doing the variation orders claims from VO 28 till VO 41.