Enter for practical for first day and introduced to the staffs. Ir. liew Chong Shing (Consultant Engineer) is my supervisor here. He firstly gave me a contract document of the Project Cadangan Membina Sebuah Kilang Memproses Daging Ayam Yang Mengandungi – 1 Blok Kilang Untuk Memproses, Menyimpan dan Pengeluaran Daging Ayam Dengan Pejabat Urusan Di Tingkat Mezzanin (PK AGRO). He asks me to go through the contract document for once and read carefully the document.
Then, Ir. Liew gave me the variation orders of this project which been submitted by the main contractor (OMORI INNOVATION). This variation orders is the additional or changes in the original contract and contains amount of claims from the contractor side.
Then, I prepared the variation orders from VO1R – VO37 in Microsoft Excel according to the contractor claims with additional consultant recommendation column for comment purpose on the claims.
On 8th April 2010, I went for site meeting & inspection at Starfeedmill CPF Company at Beranang, Selangor. I observed the way the meeting conducted among the Owner, Consultant engineer & Contractor. The project in progress there is to build a New Plant consists of Raw Material Intake Building, Feeds Transfer Tower & Link Bridges to the additional plant. I also observed the way Ir.liew did the site inspection and spot the defects of the constructions.
On 9th April 2010, i went for site visit at Toyota UMW, Shah Alam site and Kapar, Klang site. The project on going on the both sites is to build a factory and warehouse. I observe the piling method on at both sites.