Monday, May 31, 2010

Overview Week 8

Attend a site meeting at PK AGRO Site on 26th May 2010. This site meeting as usual highlighted the weekly progress and works done by the contractors. Issues highlighted such as the cables used by electrical contractor are not according to the owner requirement and asked to change it. Some of the wall plugs used are not stainless steel and rectification needed.

Then around 3pm, I went for a client meeting at SEHWA ELECTRONIC, Senawang. This meeting is for the extension building of SEHWA and layout of new factory. The matters discussed such as changes/additional areas, power supply and warehouse location.

I then continued doing the variation orders claims from VO 28 till VO 41.

Overview Week 7





On 18th May 2010, I went to Impact Factory with Engineer Nora to take some pictures of the building to submit to the local authority. Then the officer from Majlis Perbandaran Selangor will come to inspect the building according to the As-Built Drawing submitted.

Then, on 19th May 2010, I went again to the PK AGRO Project to attend a site meeting to discuss weekly progress.

Then on 20th May 2010, I continued with the Variation Order to do the recommendation on the claim prices. Ir.Liew taught me to calculate the original price referring to the contract rate from the Bill of Quantity.

On 21st May 2010, I went to Seremban 2 Site to snap some picture of the site with Engineer Nora. The proposed project is to build a 4 stories budget hotel. The pictures we snapped are mainly about the pipe water crossing and its location on site. This is to ease the contractor to remove the location of the pipes while clearing the site and doing the earthwork.

Overview Week 6




On 10 May 2010, Went for site meeting at Impact factory project at Bukit Lanchang, Petaling, Selangor. Firstly, I observe the BOMBA inspection and the way they inspect the fire fighting equipment at the factory. They checked the pump house, Bomba Hose reel pressure, the curtain wall at LV Consumer Switch Room, Control Room and HT Switch Room. For the HT Switch Room, in case of fire emergency, the CO2 gas will be release automatic after the sensor detects the smoke. For the other two rooms, the fire curtain will drop down to disallow the fire to spread into the room.

After the inspection, I attend the site meeting and this meeting mainly focused on the defects issued done by the contractor and the rectification status for updates. Some of rectification technique proposed by Ir.Liew to overcome the defects such as the roof cladding leaking, the joint of stainless steel plate not done neatly and etc.

On 12th May 2010, I attend a site meeting at PK AGRO Project. This meeting mainly focused about the progress of the project that involves main contractor and nominated sub contractor. Some of tests mainly urged by Ir.Liew for verification purpose such as blockage test, pressure test, injection test & etc. Then, I went for site inspection to observe the construction phase and the defects done by contractor. There is a slope failure done by the contractor because they excavate the soil without using the proper method such as sheet pile or open excavation.

On 14th May 2010, I went for a meeting at Chan Sow Lin, Kuala Lumpur. This meeting is to discuss and meet the contractor for the upcoming project at Jalan Tuanku Abdul Rahman, Kuala Lumpur. Some of additional & changes in the drawing explained to the contractor Mr. Patrick and many questions asked to the contractor regarding the project matters.

Overview Week 5

I went again for site meeting & inspection at the CPF Starfeedmills Company on 3rd Mar 2010. The construction phase already done and just some touch up works such as painting and fixing the defects on going at site. There is also a night visual test proposed by Ir. Liew to make sure the silo does not have any holes when handing over to the owner.

Some of electrical and mechanical works been discussed to get the finishing date for the people from Majlis Perbandaran Kajang(MPKJ) to come and inspect the site.There are also some defects highlighted for rectification purpose as below:-

1) Some of bolt hole miss location – To fix the bolt and make sure no miss out.

2) The top fin plate to top UB flange gap is larger than 6mm and in some area reached few inches. – To rectify this problem, Ir. Liew suggests adding steel plate on both side of the beam at the part it connecting to the column.

This is to stiffener the weak part as the big gap might bend the beam if there is any heavy load acting on it for example heavy machine.

The contractor also awarded (CPC) Certificate of Practical Completion by the owner dated 03rd May 2010 for insurance purpose for contractor. This is a certificate that will be awarded to the contractor upon job completion but the performance bond and the retention sum will be hold until the contractor finishes up all the remedial works.

Then, I went for a meeting at McD Sungai Besi, Kuala Lumpur on 5th may 2010. The purpose of this meeting is to discuss the roof plan that been design by Ir.liew for McD renovation project. After that, I attend another meeting at PK AGRO Company. This meeting is mainly about the variation orders claim by the electrical contractors. Meeting finished around 9.30pm.

On 6th May 2010, I went for a meeting with Koperasi Persatuan Guru-Guru Melayu Nusantara (KPGGM) at Sentul, Kuala Lumpur. This meeting is between the Jurutera Sinarunding, KPGGM and the Developer (SCH Brother). Meeting mainly focused on the land convergence discussion about the project land to the new owner, the process to start work at site and the approval from external department such as SYABAS, MAJLIS PERBANDARAN SELANGOR and many more.

Then, around 3.30pm, I went together with Engineer Lim to Majlis Perbandaran Nilai (MPN) to do the plan submission for the factory project (YOUNGREEM PROJECT) at Taman Tuanku Jaafar, Negeri Sembilan. The submission includes the plans for the Infrastructure, Building, Engineering, Environment, Waste Management, Landscape and etc.

On 7th May 2010, I went to Hulu Langat Site for site meeting and inspection. The previous visit to this site is on 16th April 2010. This meeting as per usual discussed the progress of works and problems encounter in construction stages.

Overview Week 4





On 26th April 2010, I went for site visit at Kapar, Selangor. This is the previously visited site on 9th April 2010. The piling stage almost finishes and the preparation for the pile cap carried out. The problems occurred on this site is some of the piles were labelled by Y10 at the edge of the pile. Pile size is 200 mm x 200 mm and the steel bar used in it was Y12. Confusion occurred and the piling work stopped for moment. After the confirmation obtained that the steel bar used is Y12, then the piling works continued.

I was given company profile and all the information needed typed down. Then, I continued with the variation orders for the PK AGRO Project.

On 30th April 2010, I went again to the Toyota UMW site around 1.30pm for site meeting. This meeting mainly focused on the offset problem occurred in the piling stage. One of the piles is out from the position. As a solution, another pile needs to be piled opposite of the offset pile 450mm distance from the original centre of gravity (CG) to pull back the original centre of gravity (CG). If the centre of the gravity (CG) is not in the position, later it will create problem for the structure.

Overview Week 3





On 19th April 2010, I went to site visit at Bukit Tinggi Klang, Selangor around 10am. The project finished the piling stage and we went to inspect the formwork and the steel reinforcement for the pile caps. The problem that I observed is the hole excavated for pile cap filled with water. The water need to be pumped out using the pump before the pile cap constructed as the rectification work. The steel bar coming out from the pile head also not straight and some of them bent.

On 21st April 2010, I went for a meeting at WRP Factory at Sepang, Selangor. This factory produces the surgical gloves and masks. The meeting mainly discuss about the fire incident at a warehouse at that company past one month and the necessary action that must be taken for insurance claims. Then, I went and visit the part that been caught by fire and snapped some pictures.

On 23rd April 2010, I went for a meeting at PK AGRO Company around 10am. This meeting involve the Owner of PK AGRO, Jurutera Sinarunding Aidil & Ommori Innovation. This meeting mainly discuss regarding the variation orders claims by the contractor. There is some recommendation by the consultant engineer on the price of claims. Then, the owner decides whether want to pay the amount of claims or reject it. The variation orders discussed from VO1- VO27.

Overview Week 2



I continued with the variation orders of the PK AGRO project for 3 days.

Then, on 16TH April 2010, I went for site meeting & inspection at Hulu Langat site at Cheras, Selangor. The project on going there is to build a factory 1 ½ storey (Plastic Injection) with office 3 storey, a warehouse, guard house, waste disposal area & a pump house.

The meeting mainly highlighted about the problems encounter in the construction and the works progress. Then, I went for site inspection to inspect the works done by the contractor and found many defects. For example: The roof for the guard house according to the drawing given. The fascial of the roof does not cover the roof properly and the brick wall not done till the top part of roof. To rectify this problem, the contractor instructed by Ir.Liew to redo the roof part again according to the drawing.

Overview Week 1




Enter for practical for first day and introduced to the staffs. Ir. liew Chong Shing (Consultant Engineer) is my supervisor here. He firstly gave me a contract document of the Project Cadangan Membina Sebuah Kilang Memproses Daging Ayam Yang Mengandungi – 1 Blok Kilang Untuk Memproses, Menyimpan dan Pengeluaran Daging Ayam Dengan Pejabat Urusan Di Tingkat Mezzanin (PK AGRO). He asks me to go through the contract document for once and read carefully the document.

Then, Ir. Liew gave me the variation orders of this project which been submitted by the main contractor (OMORI INNOVATION). This variation orders is the additional or changes in the original contract and contains amount of claims from the contractor side.

Then, I prepared the variation orders from VO1R – VO37 in Microsoft Excel according to the contractor claims with additional consultant recommendation column for comment purpose on the claims.

On 8th April 2010, I went for site meeting & inspection at Starfeedmill CPF Company at Beranang, Selangor. I observed the way the meeting conducted among the Owner, Consultant engineer & Contractor. The project in progress there is to build a New Plant consists of Raw Material Intake Building, Feeds Transfer Tower & Link Bridges to the additional plant. I also observed the way Ir.liew did the site inspection and spot the defects of the constructions.

On 9th April 2010, i went for site visit at Toyota UMW, Shah Alam site and Kapar, Klang site. The project on going on the both sites is to build a factory and warehouse. I observe the piling method on at both sites.

Company Profile

JURUTERA SINARUNDING AIDIL SDN BHD

COMPANY PROFILE

Jurutera Sinarunding Aidil Sdn.Bhd is a registered consulting firm offering Structural & Civil Engineering, Mechanical & Electrical Engineering services, both as a Consultant and Prime Designer, principally servicing the construction industry. We have qualified personnel with experiences and resources to provide a comprehensive range of services that respond to the technical, operational and functional requirements of our clients.

CORPORATE OBJECTIVES

Sinarunding is committed to consistent but prudent growth while maintaining a leadership role in structural & civil & mechanical & electrical engineering. To facilitate this growth, the firm is committed to helping employees develop their technical and managerial capabilities. Sinarunding aims to maintain the highest standard, both professionally and ethically, and to be technically creative while producing a consistent and thorough service.

HISTORY

Sinarunding was founded in 1997. In the earlier days, the firm has been engaged in the practice of Mechanical & Electrical consultancy services. Due to expansion program, the team of founders has incorporated a new firm – Jurutera Sinarunding Aidil Sdn. Bhd in 1999. Thus, added strong leadership and sound management of technical capabilities to develop exceptional creative and cost-effective solutions that carry a project from inception to completion.

FIRM PHILOSOPHY

Jurutera Sinarunding Aidil Sdn. Bhd believed that engineers should be able to practice with a minimum organizational restriction. This would allow each engineer to work directly and independently with his or her clients while drawing upon the experience and resources of all other professional in the firm.

At sinarunding, we strive to be an organization with the minimum number of organizational levels, giving the decision-making responsibility to those closest to the issues. Based on this philosophy, employees experience the opportunity of growth based on their own competency, attitude and commitment. Personal satisfaction is achieved through a sense of accomplished and a job well done. Consequently, we encourage open communication in all aspects of our profession and business. We strive to continually increase employee involvement by allowing every to be truly part of the development of each project. Sinarunding has experienced an outstanding record of continued growth by providing quality design and service to our clients. The growth and reputation of the firm are the direct outcome of individual efforts and close cooperation by all our employees. Our continuation of these efforts and adherence to the highest professional standards and ideas lead us as the leader in engineering for making design solution become reality.

FIRM’S STRUCTURE

Paid-up capital : RM 80,000.00

Authorized capital : RM 100,000.00

Shareholding : Ir. Liew Chong Shing

Ir.Ho Weng Kai, Ir.Mohd Nor B Abu Bakar

Professional Staff : 11

Total Staff Strength : 28

Director (Civil/Struc.) : Ir.Liew Chong Shing

Director (Mechanical) : Ir.Ho Weng Kai

Director (Electrical) : Ir.Mohd Nor B Abu Bakar

Director (Development) : Abdul Hadi law B Abdullah

Associate (Piping) : Ir Liew Huey Chyan

Associate (Architect) : Phyllis Liew Pih Yit

OUR BUSINNESS UNITS

Jurutera Sinarunding Aidil Sdn Bhd provides specialized expertise as well as integrated services to a broad variety of business and industries as well as all levels of government. We build long-term relationships with our clients and serve their needs on large and small projects nationwide. Our Business Units are:

· Client needs, goals, communication and process

· Collaborative approach with significant client involvement

· Repeat clients – making productive relationships

· Design with careful attention with in-house structural, civil, mechanical system history

· Ensuring an excellent schedule history

· Advanced CAD and presentation capabilities

· Close interaction with communities to gain project support

OUR VISION AND VALUES

The vision:

A leader in designing, building and operating infrastructure worldwide performance and customer relationships

The value:

A fundamental set of beliefs particular to Sinarunding. These values determine individual behaviors which, in turn, reinforce the values. It is with these common shared values that create the culture that supports achievement of our Vision. Sinarunding’s six core values are:

v Customer Commitment

v Safety

v Valuing our People

v Open & Honest Communication

v Teamwork

v Innovation

At Jurutera Sinarunding Sdn Bhd, we will actively drive this commitment by example: Communicating our vision, expectations and providing resources and recognition

Our Areas of Expertise

General Architectural, Engineering and Consulting In The Area Of:

Ø Infrastructure

Ø Civil

Ø Structural

Ø Mechanical

Ø Electrical

Ø Process Piping

Ø Waste Water Treatment Plant

Ø Architectural/Building

Ø Construction Services

Ø Pre-construction

Ø Construction Management

PROJECT TEAM STRUCTURE

Our concept of project implementation is the active involvement of the Project monitoring team comprising the senior members of the management. This shall ensure valuable input and quality control primarily by well experienced and qualified professional in terms of

· Guidance to project implementation

· Monitoring the progress of the project

· Reviewing the quality of the project design and drawings

· Liaison with clients to ensure coherent objectives

These are essential, indeed crucial procedures to achieve our firm’s philosophy

All projects team would comprise the following:

Ø Ir.Liew Chong Shing – Managing Director

Ø Ir.Ho Weng Kai – Director

Ø Ir.Mohd Nor Abu Bakar – Director

Ø Project Coordinator

Ø Project Engineers ( Design & Site)

Ø Technician/ Site Supervising Staff

Ø Draughting Staff

PROFESSIONAL STAFFING

Jurutera Sinarunding Aidil Sdn.Bhd recognizes and believes that the key assets are not only the sophisticate hardware’s in our design office but rather our highly trained, experienced and dedicated and loyal staff. With this recognition and our modern management style we are able to attract the industry’s best talent to enable us to give the best to you. This team of highly dedicated staff is inspired by the strong and determined leadership exemplary by our directors who are in themselves highly trained and experienced in a wide spectrum of disciplines from engineering to corporate restructuring.

PROFESSIONAL FEES AND SCHEDULE OF PAYMENT
the professional fees chargeable and its schedule of payment are in strict accordance with the professional (fees) scale structured by the Board of Engineers, Malaysia (BEM). However for specialized negotiated consultancy and full turnkey projects our fees are assuring competitive.

SOME LIST OF CURRENT AND PAST INDUSTRIAL PROJECTS IN MALAYSIA

· Proposed Brick Factory at Gemencheh, Negeri Sembilan for Pertubuhan Peladang Kawasan Tanggamas

· Proposed Transformer’s factory extension at Nilai, Negeri Sembilan for Arab-Malaysian SGB Sdn Bhd

· Proposed 88.5 acres of industrial Development at Chembong Industrial Estate (Fasa 3) for Perbadanan Kemajuan Negeri Sembilan

· Proposed Glass Manufacturing Factory (2 plots) at Klang, Selangor Darul Ehsan for Sysron Sdn Bhd

· Proposed feature roof steelwork for Great Eastern Life Assurance (M) Bhd in Jalan Ampang, Kuala Lumpur for Obayashi Coroporation

· Proposed Trolley Conveyor House at Perindustrian Tuanku Jaafar, Seremaban, Negeri Sembilan

· Proposed one 1 storey factory at Telok Gong,Klang for Maxstead Chemical Sdn.Bhd

· Proposed one block of ‘Cobblestone’ Factory at lot 1370,GM 184, Mukim Keru, Daerah Tampin, Negeri Sembilan

· Proposed one block of Tobacco product factory at lot 2485 & 2486, Oakland Industrial Park, Seremban, Negeri Sembilan Darul Khusus for Fumori industries Sdn Bhd.

SOME LIST OF CURRENT AND PAST INDUSTRIAL PROJECTS OVERSEAS

· Proposed Design & Build of various steelworks package at HERON QUAYS HQ-4, Canary Wharf, London for Cassana Steel Ltd.(London)

· Proposed Design & Build of multi-bays car park canopy at BESTWAY CASH & CARRY LIMITED, ABBEY ROAD, PARK ROYAL, LONDON NW10 for CASSANA STEEL LTD. (LONDON)

· Proposed renovation works & factory extension at Lot 195, Dai Lo Doc Lap, Vietnam Singapore Industrial Park, Vietnam for United Garment (Vietnam) Co.Ltd

· Proposed renovation works at Lot D3, Dai Lo Doc Lap, Vietnam Singapore Industrial Park, Vietnam for International Silk Printing Co.Ltd

· Proposed Calcium Carbonate Manufacturing Plant in Tutong, Negara Brunei for Puja Chemical Plant (PCP)

· Proposed Design & Build of various steelworks package at BP1, Canary Wharf, London.

· Proposed Metal Works Factory (200,000 s.f) at Lot No.18-21,IZ Danang, Andon, Danang, Vietnam for Ban Ngai Manufacturing Ltd.