report for WEEK 11
on 14th June 2010, I Went for site meeting at PK AGRO project around 3.30pm. This meeting mainly discussed about the electrical and mechanical part which mainly involve NSC (FULOOP). Few items discussed such as variations works for electrical works and air conditional variation orders. Also includes in the meeting is the time/frame schedule to complete the mezzanine office such as lighting, air conditional and many more. Fulloop defects also highlighted in this meeting such as telephone ducts, armoured cable not in G.I conduit & CCTV cable broken.
On 15th June 2010, I went to Senawang Phase 2 near Taman Widuri Indah to snap some pictures & observed the project site with Mr.Lim around 10am. This is considered as a site research to obtain the view and idea to design the platform, road & drainage, sewerage to match the existing lot at the 4 boundaries as the site located at centre. The drainage design also need to be design as it could match to the existing drainage to discharge the water to any river near the site.
Then around 1pm, I went to Shi Sei Autoparts at project at Kapar, Klang to inspect the steel column arrived at site. The size of the steel column for the big one is 533kg and the small column is 356kg. I also observed the ground beam construction & there is some part where the lean concrete poured to the ground as 3’’ thickness. At 3pm, I went to Han San factory project site at Kapar Indah to inspect the construction works whether done properly or not. Almost 60% works done at site and Ir.Liew inspects the works done according to their record given to JSA. We found some defects and Non Conformance Report delivered to the contractor as below:-
1) Internal water plumbing pipe – we specified ABS CL.15 pipe. Site use PVC Class 7 pipe. These pipes are not acceptable by SYABAS. You are required to remove and redo again.
2) External Manhole and Pipe – 2 external manholes located outside the toilets is appeared to be too shallow. You have also use non-conform pipe inside the manhole and also from the toilets. You must use BS 4660 underground as soil pipe and vitrified glazed ware pipe inside the manhole. **AS SUCH, PLEASE RE-DO THE MANHOLE AND PIPE WORK COMPLETELY!
On 16th June 2010, I attend the site meeting at PK AGRO project around 2pm. The issues that discussed in this meeting is same as discussed in the previous meeting and the status of each issued reported by the NSC. Then after the meeting over, the owner show some slide presentation for the technical man who came from the Main Plant from Thailand. The presentation includes the internal and external machine used in the factory and the interior design pattern for the factory’s office.
On 17th June 2010, I went to Principle Perspective Engineering S/B for a project meeting. This PPE Company is specialise in construction field and located at Banting, Selangor. This meeting is between the construction firm owner, Mr.Loke and us. It is regarding a American Solar Panel factory project (Phase 2) that will be kick off on 15th July 2010. Ir.Liew recommended by Mr.Loke to the Owner as the consultant engineer for this project. The phase 1 of the project is still in progress and the area for the phase 2 is behind the phase 1 area. This is a very large factory which the land for the phase 2 covers up till 45,000 m2. The main contractor for this project will be in 2 teams which are PPE and Fluor Daniel (from US). PPE covers the architect, civil and structure while Fluor Daniel covers mechanical, electrical and processing.
Then around 2pm, I went to Ng Boon Seng factory project site at Telok Panglima Garang. The works at the site is still in progress. The steel roof and column for both block A& B already done. For the office area, the RC body structure already had done partly outer part such as the beams, columns and slabs.
On 18th June 2010, I went for YoungReem project site at Taman Tuanku Jaafar, Neg.Sembilan to observe the works in progress at site. I observed the piling works & they were using the Hume RC pile size 150mmx150mm and 200mm x 200mm. Then, I went to observe the pile cap construction as the concrete mixer arrived and pour the mixture into the formworks. Then, I also observed the steel bars at the site which has many types such as high tensile steel bar Y12, Y16, Y20 and Y25. I also observed the steel bars bending process to be use as reinforcement in the pile cap construction.