On 18th May 2010, I went to Impact Factory with Engineer Nora to take some pictures of the building to submit to the local authority. Then the officer from Majlis Perbandaran Selangor will come to inspect the building according to the As-Built Drawing submitted.
Then, on 19th May 2010, I went again to the PK AGRO Project to attend a site meeting to discuss weekly progress.
Then on 20th May 2010, I continued with the Variation Order to do the recommendation on the claim prices. Ir.Liew taught me to calculate the original price referring to the contract rate from the Bill of Quantity.
On 21st May 2010, I went to Seremban 2 Site to snap some picture of the site with Engineer Nora. The proposed project is to build a 4 stories budget hotel. The pictures we snapped are mainly about the pipe water crossing and its location on site. This is to ease the contractor to remove the location of the pipes while clearing the site and doing the earthwork.